Conversion of 33Kv over Head Power Line Crossings into under Ground Cable Crossings... Tender

SOUTH CENTRAL RAILWAY has floated a tender for Conversion of 33Kv over Head Power Line Crossings into under Ground Cable Crossings in Sc-Kzj Sections of Sc Division.. The project location is SECUNDERABAD, Telangana, India. The reference number is C-E29-TRD-33-2023-24 and it is closing on 11 Mar 2024. Suppliers can request Register free of cost to get the complete Tender details and download the document.

Expired Tender

Procurement Summary

State : Telangana

Summary : Conversion of 33Kv over Head Power Line Crossings into under Ground Cable Crossings in Sc-Kzj Sections of Sc Division.

Deadline : 11 Mar 2024

Other Information

Notice Type : Tender

TOT Ref.No.: 96988736

Document Ref. No. : C-E29-TRD-33-2023-24

Competition : NCB

Financier : Self Financed

Purchaser Ownership : Public

Document Fees : Refer Document

Tender Value : ₹ 6896172.00

EMD : ₹ 137900.00

Purchaser's Detail

Name :Login to see tender_details

Address : Login to see tender_details

Email : Login to see tender_details

Login to see details

Tender Details

Supply, providing, erection, testing and commissioning of 800 Amps, 33kV AB switch assembling etc. 2 Please see Item Breakup for details. 102000.00 AT Par 102000.00
Contract Type : Works
Tender Type : Open
Advertised Value : 6896172.00
Bidding Style : Single Rate for Each Schedule
Bidding System : Single Packet System
Pre-Bid Required : No
Pre-Bid Query Date Time : Not Applicable
Tendering Section : WORKS
Bidding Unit :
Publishing Date / Time : 15/02/2024 15:39
Period Of Completion : 90 Days
Bidding Start Date : 26/02/2024
Closing Date Time : 11/03/2024 15:00
Validity of Offer ( Days) : 60
Are Joint Venture (JV) firms allowed to bid : -
Tender Doc. Cost (Rs.) : 0.00
Earnest Money (Rs.) : 137900.00

Documents

 Tender Notice

viewNitPdf_4475651.pdf

GCC_April-2022_1.pdf

Mastertenderbooklet2TRDV01_1.pdf

Mastertenderdocument1TRDV0_1.pdf

similarnatureofworksHQlr2014.pdf

SCCandTechnicalspec33-2023-24.pdf

ExplanatoryNotes33-2023-24.pdf

Scopeofwork33-2023-24_1.pdf