Procurement Summary
State : Jharkhand
Summary : Work for Conversion of Existing 3.3Kv Bus-Bar of Ara-Kanta Substation into 11Kv Bus-Bar, Dismantling of Complete 3.3Kv Oh Line from Ara -Kanta Substation to Dumerbera Substation and Installation of T...
Deadline : 06 May 2024
Other Information
Notice Type : Tender
TOT Ref.No.: 100493298
Document Ref. No. : GM (K)/EnM/eTender/24-25/01
Competition : NCB
Financier : Self Financed
Purchaser Ownership : Public
Document Fees : Refer Document
Tender Value : Refer Document
EMD : ₹ 14800
Purchaser's Detail
Name :Login to see tender_details
Address : Login to see tender_details
Email : Login to see tender_details
Login to see detailsTender Details
Work for Conversion of Existing 3.3Kv Bus-Bar of Ara-Kanta Substation into 11Kv Bus-Bar, Dismantling of Complete 3.3Kv Oh Line from Ara -Kanta Substation to Dumerbera Substation and Installation of Transformers at Ara Kanta Substaion.
Work for conversion of existing 3.3KV Bus-Bar of Ara-Kanta substation into 11KV Bus-bar, dismantling of complete 3.3KV OH Line from Ara -Kanta substation to Dumerbera substation and installation of transformers at Ara kanta substaion
Electrical and Maintenance Works
Tender ID : 2024_CCL_307104_1
Tender Category : Works
Product Category : Electrical and Maintenance Works
Sub Category : NA
Form Of Contract : Item Rate
Contract Type : Tender
Bid Validity(Days) : 120
Period Of Work(Days) : 15
Document Download / Sale Start Date : 26-Apr-2024 06:55 PM
Document Download / Sale End Date : 06-May-2024 06:55 PM
Bid Submission End Date : 06-May-2024 06:55 PM
Bid Opening Date : 07-May-2024 11:00 AM
EMD Amount in ₹ : 14, 800
Tender Value in ₹ : NA