Procurement Summary
Country : China
Summary : Boiler Rain Cover, Silencer and Expansion and Exhaust Pipe Support Frame Corrosion Control
Deadline : 16 Oct 2024
Other Information
Notice Type : Tender
TOT Ref.No.: 108206662
Document Ref. No. : 0724-2420N2476149
Competition : ICB
Financier : Self Financed
Purchaser Ownership : Public
Tender Value : Refer Document
Purchaser's Detail
Name :Login to see tender_details
Address : Login to see tender_details
Email : Login to see tender_details
Login to see detailsTender Details
Tenders are invited for Boiler Rain Cover, Silencer and Expansion and Exhaust Pipe Support Frame Corrosion Control
Guangdong Yue Electric Jinghai Power Generation Co., Ltd.#1, 2, 3 Boiler Rainproof Large Cover, Mufflers and Dredging of the Support Frame Corrosion Management Announcement
Project Overview:
Guangdong Yudean Jinghai Power Generation Co., Ltd. (Huilai Power Plant) is located on the shore of Jinghai Bay in the South China Sea, at the eastern end of Huilai County, Jieyang City, Guangdong Province, 2km away from Jinghai Town and 25km away from Huilai County . The first phase of the project, Units 1 and 2, 2 × 600MW, and Units 3 and 4, 2 × 1000MW ultra-supercritical coal-fired power generation units, have been put into operation.
(II) Scope of Bidding: Jinghai Power Generation Company is located in a geographical location with typhoons, continuous rain, high temperature, rainstorms, etc. It is exposed to the above climate changes for a long time, with large temperature difference during the day, high humidity environment for a long time, and salt mist in the sea breeze. Some areas of the horizontal, vertical, inclined steel beams, silencers and expansion and exhaust pipe support and limit steel structures of the #1, 2, and 3 boilers of this plant have been seriously corroded and perforated, and need to be polished for corrosion protection and replaced; the insulation of the # 1 and # 2 boiler expansion and exhaust pipes has deformed and slid down seriously, and the steam ejected from the #1, 2, and 3 expansion and exhaust pipes has corroded the steel structure around the pipe outlet. This project adopts a contracting method of labor and materials. For details, please refer to the technical specifications of the bidding documents and shall prevail.
(III) Construction period: 90 days ( to be implemented in 2024 during the unit maintenance period). Please refer to the technical part of the bidding documents for details and it shall prevail
[Disclaimer: The above text is machine translated. For accurate information kindly refer the original document.]