REGIÃO ADMINISTRAT­IVA ESPECIAL DE MACAU. has floated a tender for Construction of an Aerial Corridor on Avenida do Nordeste. The project location is Macao and the tender is closing on 20 Mar 2024. The tender notice number is , while the TOT Ref Number is 96744479. Bidders can have further information about the Tender and can request the complete Tender document by Registering on the site.

Expired Tender

Procurement Summary

Country : Macao

Summary : Construction of an Aerial Corridor on Avenida do Nordeste

Deadline : 20 Mar 2024

Other Information

Notice Type : Tender

TOT Ref.No.: 96744479

Document Ref. No. :

Competition : ICB

Financier : Self Financed

Purchaser Ownership : Public

Tender Value : Refer Document

Purchaser's Detail

Name :Login to see tender_details

Address : Login to see tender_details

Email : Login to see tender_details

Login to see details

Tender Details

Tenders are invited for Construction of an Aerial Corridor on Avenida do Nordeste

- 1st mandatory target: completion of the pile foundations of the first phase, with a maximum execution period of 240 (two hundred and forty) working days, counting from the date of consignment of the work;

- 2nd mandatory target: completion of the concrete and steel structures of the first phase, with a maximum execution period of 570 (five hundred and seventy) working days, counting from the date of assignment of the work.

- 3rd mandatory target: completion of all remaining work in the first phase (including architecture, remodeling and installation of electromechanical equipment) with opening and operating conditions, with a maximum execution period of 660 (six hundred and sixty) working days, counted from the date of consignment of the work;

- 4th mandatory target: completion of the pile foundations of the second phase, with a maximum execution period of 390 (three hundred and ninety) working days, counting from the date of consignment of the work;

- 5th mandatory target: completion of the concrete and steel structures of the second phase, with a maximum execution period of 630 (six hundred and thirty) days of work, counting from the date of assignment of the work.

16. Validity period of proposals: 90 (ninety) days, counting from the closing date of the public tender, extendable in accordance with article 93 of Decree-Law no. 74/99/M, of November 8th.

17. Provisional deposit: $5, 300, 000.00 (five million and three hundred thousand patacas), to be provided by means of a cash deposit, bank guarantee or security deposit approved in accordance with the law.

18. Definitive deposit: 5% of the total award price (from the amounts that the contractor has to receive, in each of the partial payments, 5% is deducted to guarantee the contract, in addition to the definitive deposit provided).

[Disclaimer: The above text is machine translated. For accurate information kindly refer the original document.]