Procurement Summary
Country : Bhutan
Summary : Construction of Rrm Retaining Wall with Anchored Rcc Toe Wall at Ch. 26.00 Km on Rinchending-Pasakha-Manitar Pnh under Monsoon Works
Deadline : 23 Feb 2025
Other Information
Notice Type : Tender
TOT Ref.No.: 114124962
Document Ref. No. : DoST/RoP/2024-2025/Mtc-09/23
Competition : NCB
Financier : Self Financed
Purchaser Ownership : Public
Tender Value : Refer Document
Purchaser's Detail
Name :Login to see tender_details
Address : Login to see tender_details
Email : Login to see tender_details
Login to see detailsTender Details
Category : Engineering works and construction works; Works for complete or part construction and civil engineering work;
Package Description : Construction of RRM Retaining Wall with Anchored RCC Toe Wall at Ch. 26.00 Km on Rinchending-Pasakha-Manitar PNH under Monsoon Works
Package Details:
Procurement Category : Works
Type of Emergency : Normal
Package No : Rinchending Section - 7 (RPM-5)
Package Description : Construction of RRM Retaining Wall with Anchored RCC Toe Wall at Ch. 26.00 Km on Rinchending-Pasakha-Manitar PNH under Monsoon Works
Work Type : Small
Work Category : W1
Deposit work / Planned work :
Tender Dates:
Expected Date of Advertisement of Tender on e-GP website : 02-Feb-2025
Expected Date of submission of Tender : 23-Feb-2025
Expected Date of Opening of Tender : 23-Feb-2025
Expected Date of Submission of Evaluation Report : 26-Feb-2025
Expected Date of Approval for Award of Contract : 03-Mar-2025
Expected Date of Letter of Intent to Award : 03-Mar-2025
Expected Date of Issuance of the Letter of Acceptance (LOA) : 13-Mar-2025
Expected Date of Signing of Contract : 13-Mar-2025
Expected Date of Completion of Contract : 29-May-2025
Total Time to Contract Signing : 39
Documents
Tender Notice