Description
RFI #1 for Project 635-CSI-022 / MRI LinacQ1. Do we need to bid the selective demo thru a core demolition contractor or GC?Q1 Response: The means and methods are up to the General Contractor to determine. OKC VAMC confirmsQ2. Will this project need any asbestos abatement on the flooring or ceiling demo?Q2 Response: There is not believed to be asbestos abatement required. OKC VAMC concurs, no asbestos in any area for this project.Q3. I attended the pre-bid site visit yesterday and there was mention of demolishing a portion of the North wall, as shown in the screenshot below, to remove the existing equipment and to move in the new equipment. However, the drawings do not indicate this, and only show the penetration for the new Quench Pipe. Could you please clarify whether the wall (including 3 6 concrete barrier) will be demoed, or if the equipment will be removed and brought in through the existing doors.Q3 Response: Demolition at the North Wall is only for the Quench Pipe condition. Equipment shall be removed and brought through the existing exit door leading directly to the outside. OKC VAMC has verified this is the correct.Q4. HVAC:a) Do they want the new HVAC equipment to have stand-alone controls or will it be connected to the base building EMS/BAS control system? If it is to be connected base building control system will the engineer be furnishing a desired control point drawing? Whom shall we contact for base building control pricing?Q4a Response: Refer to specification section 23 09 23 Direct Digital Controls. You need to contact the local JCI rep.b) The attached chilled water requirements table is from the Viewray planning guide. Please note that the Linac equipment (HCU-PE & HCU-SE) are the only two pieces of equipment that require a continuous chilled water supply. The remaining MRI equipment all has an intermittent chilled water demand. The total continuous chilled water demand (3.6 GPM min.) and the total continuous btu/h heat load ( 54, 59...
Active Contract Opportunity
Notice ID : 36C25923R0031
Related Notice
Department/Ind. Agency : VETERANS AFFAIRS, DEPARTMENT OF
Sub-tier : VETERANS AFFAIRS, DEPARTMENT OF
Office : NETWORK CONTRACT OFFICE 19 (36C259)
General Information
Contract Opportunity Type: Solicitation (Updated)
All Dates/Times are: (UTC-07:00) MOUNTAIN STANDARD TIME, DENVER, USA
Updated Published Date: Mar 10, 2023 01:01 pm MST
Original Published Date: Feb 08, 2023 12:02 pm MST
Updated Date Offers Due: Mar 31, 2023 02:00 pm MDT
Original Date Offers Due: Feb 27, 2023 02:00 pm MST
Inactive Policy: Manual
Updated Inactive Date: Apr 30, 2023
Original Inactive Date: May 28, 2023
Initiative: None
Classification
Original Set Aside:
Product Service Code: Z2DA - REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES
NAICS Code: 236220 - Commercial and Institutional Building Construction
Place of Performance:
Documents
Tender Notice
S04--Site-Visit-Meeting-Agenda.docx
S04-Site-Walk-Sign-In.pdf
36C25923R0031-0003.docx
36C25923R0031-0002.docx
36C25923R0031-0001.docx
S02-Attach--Calculation-Worksheet-for-Self-Performed-and-Subcontracted-Work-12-13-22.docx
S02-Attachment--Past-Performance-Questionnaire-12-13-22.docx
CD-Bid-Set--MRI-Linac--Specifications.pdf
CD-Bid-Set--MRI-Linac--Drawings.pdf
36C25923R0031_1.docx