Procurement Summary
Country : Canada
Summary : Structural Health Monitoring Design for Altawan Dam Structures
Deadline : 07 Aug 2024
Other Information
Notice Type : Tender
TOT Ref.No.: 103993948
Document Ref. No. : WSA-2024-25-0078
Competition : ICB
Financier : Self Financed
Purchaser Ownership : Public
Tender Value : Refer Document
Purchaser's Detail
Name :Login to see tender_details
Address : Login to see tender_details
Email : Login to see tender_details
Login to see detailsTender Details
The primary objective of this project is to evaluate the structural performance and design a comprehensive structural health monitoring (SHM) program for the Altawan Dam Structures. This includes first conducting a background study, site inspections, and structural stability evaluation to determine the SHM needs for the Altawan Dam Structures. Following this, a comprehensive SHM program will be designed. The project will be divided into two phases: (a) Phase 1: Background Study, Inspection, and Stability Evaluation Phase 1 will include a comprehensive structural site inspection, reviewing existing data, identifying knowledge gaps, and conducting a structural stability analysis of the concrete spillway. (b) Phase 2: Detailed Design of SHM Program Phase 2 will include a design of a SHM program, including instrumentation and identifying monitoring criteria. Phase 3 which includes the field installation of the designed SHM system is not included in the scope of this RFQ. However, WSA may enter into an agreement for Phase 3 deliverables with the successful consultant. WSA makes no guarantee of exclusivity or volume of work to be awarded beyond the scope of this RFQ. Phase 3 would include procuring, installing, and commissioning of instrumentation based on an accepted designed SHM program. 1.2 RFQ
The primary objective of this project is to evaluate the structural performance and design a comprehensive structural health monitoring (SHM) program for the Altawan Dam Structures. This includes first conducting a background study, site inspections, and structural stability evaluation to determine the SHM needs for the Altawan Dam Structures. Following this, a comprehensive SHM program will be designed. The project will be divided into two phases: (a) Phase 1: Background Study, Inspection, and Stability Evaluation Phase 1 will include a comprehensive structural site inspection, reviewing existing data, identifying knowledge gaps, and conducting a structural stability analysis of the concrete spillway. (b) Phase 2: Detailed Design of SHM Program Phase 2 will include a design of a SHM program, including instrumentation and identifying monitoring criteria. Phase 3 which includes the field installation of the designed SHM system is not included in the scope of this RFQ. However, WSA may enter into an agreement for Phase 3 deliverables with the successful consultant. WSA makes no guarantee of exclusivity or volume of work to be awarded beyond the scope of this RFQ. Phase 3 would include procuring, installing, and commissioning of instrumentation based on an accepted designed SHM program. 1.2 RFQ
Additional Information:
WSA is a Treasury Board Crown corporation within the meaning of The Crown Corporations Act, 1993 (Saskatchewan) that is governed by The Water Security Agency Act (Saskatchewan). WSA is responsible for water management in the Province of Saskatchewan, which includes managing the Province’s water supply, protecting water quality, ensuring safe drinking water and the treatment of wastewater, reducing flood and drought damage, protecting aquatic habitat, and managing 73 dams and related supply channels.
Competition Type: Request for Quotation
Open Date : Jul 10, 2024 03:30 PM CST
Close Date : Aug 07, 2024 04:00 PM CST
Documents
Tender Notice